Study of factors affecting the performance of construction projects in AEC industry
29 sty 2021
O artykule
Kategoria artykułu: Research Paper
Data publikacji: 29 sty 2021
Zakres stron: 2275 - 2282
Otrzymano: 24 gru 2019
Przyjęty: 08 maj 2020
DOI: https://doi.org/10.2478/otmcj-2020-0022
Słowa kluczowe
© 2020 Saurav Dixit, published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Fig. 1

Fig. 2

Fig. 3

Attributes identified from the literature affecting the performance of construction projects
1 | Willingness to adopt change, interpersonal skills, skilled labour, the commitment of the team to the project | |
2 | Jung et al. (2016), | Location constraint of project, lack of proper planning, experience of the project team, tendency to pass on the blame to others |
3 | Management, technology, labour availability, climate, education and experience | |
4 | Inaccurate productivity estimation of equipment, understanding of responsibilities by various project participants | |
5 | Managing emotions of the team, understanding of responsibilities by various project participants, social skills of key team managers | |
6 | unexpected weather condition, poor productivity of labour, inaccurate material estimate, selection of PM with a proven track record | |
7 | Design variation, conflicts among various team members, use of inappropriate planning tools and techniques, timely decision by the owner |
Exploratory factor analysis
Site management and coordination | 18% | |
Shortage of materials | 0.65 | |
Shortage of equipment | 0.85 | |
Inaccurate productivity estimation of equipment | 0.80 | |
Poor productivity of labour | 0.68 | |
Design variation | 0.85 | |
Use of inappropriate planning tools and techniques | 0.67 | |
Leadership and financial management | 11.8% | |
The timely decision by the owner | 0.48 | |
The tendency to pass on the blame to others | 0.57 | |
Understanding of responsibilities by various project participants | 0.57 | |
Conflicts among various team members | 0.54 | |
Interest and inflation rates | 0.46 | |
9.1% | ||
Unexpected weather condition | 0.55 | |
Inaccurate material estimate | 0.79 | |
Location constraint of project | 0.67 | |
Lack of proper planning | 0.61 | |
Experience of the project team | 0.55 | |
8.5% | ||
Selection of PM with a proven track record | 0.49 | |
Willingness to adopt change | 0.63 | |
The commitment of the team to the project | 0.49 | |
Skilled labour | 0.40 | |
7.5% | ||
Understanding of responsibilities by various project participants | 0.61 | |
Managing emotions of the team | 0.40 | |
Social skills of key team managers | 0.72 | |
0.60 | ||
Total variance explained | 54.5% |
Reliability analysis/Cronbach's alpha for different factors
Factor 1 (site management and coordination) | 0.92 | 06 |
Factor 2 (leadership and financial management) | 0.84 | 05 |
Factor 3 (planning) | 0.81 | 05 |
Factor 4 (commitment) | 0.90 | 04 |
Factor 5 (communication) | 0.84 | 04 |