Enhancing Project Delivery in Gaindakot Municipality, Nepal, Through the Bromilow Time-Cost Model: A Strategic Mitigation Approach
Data publikacji: 17 maj 2025
Zakres stron: 107 - 117
Otrzymano: 20 kwi 2025
Przyjęty: 02 maj 2025
DOI: https://doi.org/10.2478/bjreecm-2025-0009
Słowa kluczowe
© 2025 Shankar Kandel et al., published by Sciendo
This work is licensed under the Creative Commons Attribution 4.0 International License.
Construction projects rely on the precise interplay of time and cost to achieve success. This study explores this critical relationship, exploring how contract size influences these vital metrics and proposes data-driven mitigation strategies to ensure projects resonate with optimal performance. This study employs Bromilow’s time-cost model to investigate the relationship between project duration and expenditure. A statistically significant positive correlation was found, with a linear regression model showing a strong association (