Construction mediation and its hybridization: the case of the Hong Kong construction industry
oraz
22 cze 2017
O artykule
Kategoria artykułu: Research Article
Data publikacji: 22 cze 2017
Zakres stron: 1528 - 1536
Otrzymano: 15 gru 2016
Przyjęty: 10 maj 2017
DOI: https://doi.org/10.1515/otmcj-2016-0015
Słowa kluczowe
© 2017 Pui-Lam Ng et al., published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.
Fig. 1

Cost claim categories_
CC 1 | Ambiguity in documents |
CC 2 | Construction method change due to Engineer’s comments (on Contractor’s method statement) |
CC 3 | Error in setting out due to incorrect data shown on drawings |
CC 4 | Rectification of damage caused by excepted risks |
CC 5 | Disposal of fossils |
CC 6 | Facilities provided to other contractors, in excess of those anticipated at the tender stage |
CC 7 | Additional tests (to verify compliance with specifications, in excess of those anticipated at the tender stage) |
CC 8 | Uncovering of works for examination |
CC 9 | Delayed possession of works |
CC 10 | Acceleration of works |
CC 11 | Suspension of works |
CC 12 | Additional work (to other parts of the works) arising from repairs or defects |
CC 13 | Investigation of alleged defects |
CC 14 | Interest on claims due to their late valuation |
CC 15 | |
CC 15A | – |
CC 15B | – |
CC 15C | – |
CC 15D | – |
CC 15E | – |
CC 16 | Employer’s breach of contract |
CC 17 | Variations (including Engineer’s instruction to change) |
CC 18 | |
CC 18A | – Delay caused by additional/unforeseen government departmental procedures and late issue of consent |
CC 18B | – Overbreaks on cutting slopes |
CC 18B+CC 18C | – Delays caused by unforeseeable obstructions to foundation constructions |
CC minor | – Delays due to variations |
– Incorporation of categories where claims were relatively “minor” |
Time claim categories_
TC 1 | Inclement weather |
TC 2 | Hoisting of typhoon signal no. 8 or above |
TC 3 | Instruction issued to resolve discrepancy |
TC 4 | Variation Order |
TC 5 | Substantial increase in quantity of any work item not resulting from a variation |
TC 6 | Delayed possession of site |
TC 7 | Disruption to regular progress due to: |
TC 7A | – |
TC 7B | – |
TC 7C | – |
TC 7D | – |
TC 7E | – |
TC 8 | Suspension of works by the Employer |
TC 9 | Delay caused by an utility services organization |
TC 10 | Excepted risks |
TC 11 | |
TC 11A | – Disruption to regular progress due to additional/unforeseen government departmental procedures, or late consent |
TC 11B | – Disruption to regular progress due to unforeseeable obstructions |