CC 1 | Ambiguity in documents |
CC 2 | Construction method change due to Engineer’s comments (on Contractor’s method statement) |
CC 3 | Error in setting out due to incorrect data shown on drawings |
CC 4 | Rectification of damage caused by excepted risks |
CC 5 | Disposal of fossils |
CC 6 | Facilities provided to other contractors, in excess of those anticipated at the tender stage |
CC 7 | Additional tests (to verify compliance with specifications, in excess of those anticipated at the tender stage) |
CC 8 | Uncovering of works for examination |
CC 9 | Delayed possession of works |
CC 10 | Acceleration of works |
CC 11 | Suspension of works |
CC 12 | Additional work (to other parts of the works) arising from repairs or defects |
CC 13 | Investigation of alleged defects |
CC 14 | Interest on claims due to their late valuation |
CC 15 | Disruption to regular progress due to : |
CC 15A | – late instructions |
CC 15B | – variations |
CC 15C | – opening for inspection |
CC 15D | – delay caused by any person or organization employed by the Employer |
CC 15E | – late delivery of materials by the Employer |
CC 16 | Employer’s breach of contract |
CC 17 | Variations (including Engineer’s instruction to change) |
CC 18 | Other reasons |
CC 18A | – Delay caused by additional/unforeseen government departmental procedures and late issue of consent |
CC 18B | – Overbreaks on cutting slopes |
CC 18B+CC 18C | – Delays caused by unforeseeable obstructions to foundation constructions |
CC minor | – Delays due to variations |
– Incorporation of categories where claims were relatively “minor” |