Impact of Takt-Time Planning on Plastering Work Productivity: A Case Study
y
29 dic 2023
Acerca de este artículo
Publicado en línea: 29 dic 2023
DOI: https://doi.org/10.2478/sspjce-2023-0002
Palabras clave
© 2023 Mária Kozlovská et al., published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 3.0 License.
This article aims to analyze productivity issues during the implementation of plastering works on the case study of a residential complex. The results of the study revealed that establishing a proper work schedule and adhering to the Takt schedule resulted in a 19% increase in plastering productivity compared to non-Takt schedules. Furthermore, the study identified the existence of waste, which had a negative impact on the progress of the plastering work and could have been prevented through better project planning during the initial project phases.