An integration of spreadsheet and project management software for cost optimal time scheduling in construction
y
29 dic 2017
Acerca de este artículo
Categoría del artículo: Research Article
Publicado en línea: 29 dic 2017
Páginas: 1627 - 1637
Recibido: 14 nov 2017
Aceptado: 24 nov 2017
DOI: https://doi.org/10.1515/otmcj-2016-0028
Palabras clave
© 2017 Tadej Valenko et al., published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.
Fig. 1:

Fig. 2:

Fig. 3:

Fig. 4:

Fig. 5:

Fig. 6:

Fig. 7:

Fig. 8:

Fig. 9:

Fig. 10:

Figure 11:

Duration and direct costs of activities_
A | 1 | 2 | 280000 | 180000 | (380–100TA) × 103 |
B | 2 | 4 | 420000 | 320000 | (520–50TB) × 103 |
C | 7 | 10 | 860000 | 620000 | (1420–80TC) × 103 |
D | 4 | 6 | 340000 | 260000 | (500–40TD) × 103 |
E | 3 | 4 | 570000 | 410000 | (1050–160TE) × 103 |
F | 3 | 5 | 260000 | 180000 | (380–40TF) × 103 |
G | 4 | 7 | 1020000 | 900000 | (1180–40TG) × 103 |
H | 6 | 9 | 380000 | 200000 | (740–60TH) × 103 |
I | 5 | 7 | 270000 | 210000 | (420–8300TL) × 103 |
J | 6 | 8 | 490000 | 430000 | (670–30TJ) × 103 |
K | 3 | 4 | 200000 | 160000 | (320–40TK) × 103 |
L | 3 | 5 | 350000 | 250000 | (500–50TL) × 103 |
M | 1 | 2 | 200000 | 100000 | (300–100TM) × 103 |
N | 3 | 6 | 510000 | 330000 | (690–60TN) × 103 |