An integration of spreadsheet and project management software for cost optimal time scheduling in construction


Zitieren

Fig. 1:

Project options.
Project options.

Fig. 2:

Import wizard.
Import wizard.

Fig. 3:

Usage steps of proposed integration of spreadsheet and PMS.
Usage steps of proposed integration of spreadsheet and PMS.

Fig. 4:

Input data in Microsoft Excel.
Input data in Microsoft Excel.

Fig. 5:

Array of activities.
Array of activities.

Fig. 6:

Changing cells.
Changing cells.

Fig. 7:

Settings in Solver.
Settings in Solver.

Fig. 8:

Output file.
Output file.

Fig. 9:

Optimal time schedule for example project.
Optimal time schedule for example project.

Fig. 10:

Updated optimal solution for example project.
Updated optimal solution for example project.

Figure 11:

Updated time schedule for example project.
Updated time schedule for example project.

Duration and direct costs of activities.

Activity IDDuration [weeks]Direct costDirect cost–duration function
Option 1Option 2Option 1Option 2
A12280000180000(380–100TA) × 103
B24420000320000(520–50TB) × 103
C710860000620000(1420–80TC) × 103
D46340000260000(500–40TD) × 103
E34570000410000(1050–160TE) × 103
F35260000180000(380–40TF) × 103
G471020000900000(1180–40TG) × 103
H69380000200000(740–60TH) × 103
I57270000210000(420–8300TL) × 103
J68490000430000(670–30TJ) × 103
K34200000160000(320–40TK) × 103
L35350000250000(500–50TL) × 103
M12200000100000(300–100TM) × 103
N36510000330000(690–60TN) × 103