Supply chain management and lean concept in construction: a case of Ghanaian building construction industry
31 gru 2019
O artykule
Kategoria artykułu: Research Paper
Data publikacji: 31 gru 2019
Zakres stron: 2034 - 2043
Otrzymano: 11 lip 2019
Przyjęty: 28 lis 2019
DOI: https://doi.org/10.2478/otmcj-2019-0010
Słowa kluczowe
© 2019 Ali Boateng, published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Characteristics of case projects
Construction of 4-Storey Examination Block | 5,500,000 | Berock Ventures Limited |
Construction of 4-Storey N-Block for the College of Engineering | 6,200,000 | Berock Ventures Limited |
Construction of VIP Ward for KNUST Hospital | 2,200,000 | Stivo Company Limited |
Construction of 3-Storey Computer Laboratory and Canteen Block for KNUST JHS | 1,500,000 | Asib Company Limited |
Level of coordination and collaboration among industry players
Consultants | 63 | 4.48 | 0.602 | 0.131 |
Subcontractors | 63 | 3.90 | 0.944 | 0.206 |
Major suppliers | 63 | 4.14 | 0.910 | 0.199 |
Clients | 63 | 4.67 | 0.483 | 0.105 |
Coordination in planning of activities
Consultants | 63 | 4.57 | 0.746 | 0.163 |
Subcontractors | 60 | 3.65 | 1.137 | 0.254 |
Major suppliers | 60 | 3.30 | 1.380 | 0.309 |
Clients | 60 | 4.20 | 1.005 | 0.225 |
Respondents information
Profession of respondents | ||
Quantity surveyor | 24 | 38 |
Architect | 24 | 38 |
Engineer | 3 | 5 |
Project manager | 12 | 19 |
Total | 63 | 100 |
Academic qualification | ||
MSc/MPhil/MTech | 25 | 40 |
BSc/BEng/BTech | 36 | 57 |
HND | 2 | 3 |
Total | 63 | 100 |
Years of experience | ||
Below 5 years | 2 | 3 |
5–10 years | 18 | 29 |
10–15 years | 19 | 30 |
15–20 years | 12 | 19 |
Above 20 years | 12 | 19 |
Total | 63 | 100 |
Sources of waste
A | Delays in arrival of workers, plant and materials | 63 | 3.7619 | 0.70034 | 0.15283 |
B | Slow decision-making and instructions by consultants | 63 | 3.6190 | 0.74001 | 0.16148 |
C | Waste of materials | 63 | 3.5238 | 0.74960 | 0.16358 |
D | Shortage of materials | 63 | 3.5238 | 0.87287 | 0.19048 |
E | Inefficient movement of workers | 63 | 3.3810 | 0.80475 | 0.17561 |
F | Poorly scheduled delivery of materials to site | 63 | 3.2857 | 0.84515 | 0.18443 |
G | Accidents | 63 | 3.2381 | 0.62488 | 0.13636 |
H | Excess materials in store | 63 | 3.1905 | 0.92839 | 0.20259 |
I | Waiting and idling | 63 | 3.1905 | 0.92839 | 0.20259 |
J | Double handling of materials | 63 | 3.1429 | 0.91026 | 0.19863 |
K | Use of materials over and above specifications | 63 | 3.1429 | 0.96362 | 0.21028 |
L | Deterioration of materials | 63 | 3.0952 | 0.76842 | 0.16768 |
M | Rework | 63 | 3.0476 | 0.80475 | 0.17561 |
N | Unnecessary or not enough information flow | 63 | 3.000 | 0.89443 | 0.19518 |
O | Waste of space on-site | 63 | 2.9524 | 0.74001 | 0.16148 |
P | Defects | 63 | 2.9524 | 0.74001 | 0.16148 |
Q | Work not done | 63 | 2.9524 | 0.86465 | 0.18868 |
R | Over allocation of materials to an activity | 63 | 2.9524 | 0.97346 | 0.21243 |
S | Unnecessary work | 63 | 2.9048 | 0.88909 | 0.19401 |
T | Poor quality of materials | 63 | 2.8571 | 0.79282 | 0.17301 |
U | Poor storage of materials | 63 | 2.8095 | 0.74960 | 0.16358 |
V | Workers performing activities well below their capabilities | 63 | 2.8095 | 0.87287 | 0.19048 |
W | Abnormal use of equipment and tools | 63 | 2.7143 | 0.84515 | 0.18443 |
X | Inadequate storage spaces | 63 | 2.7143 | 0.84515 | 0.18443 |
Communication and information sharing
Consultants | 57 | 4.68 | 0.478 | 0.110 |
Subcontractors | 60 | 4.30 | 0.571 | 0.128 |
Major suppliers | 60 | 4.25 | 0.550 | 0.123 |
Clients | 63 | 4.43 | 0.746 | 0.163 |