Forecasting operational costs of technical objects based on the example of railbuses


Zacytuj

Introduction

Operational costs of a technical object

The term technical object (exploitation object) refers to products serving as a tool for transforming (moving or processing) matter, energy or information. This term is usually used to describe machines, devices and means of transport.

, i.e., the costs incurred in the course of operation (use) of an object, represent one of the three categories of exploitation costs (service life costs). In addition to operational costs, exploitation costs of an object cover (Adamkiewicz, 1983; Dietrich et al., 1999; PN-EN 60300-3-3, 2001):

damage costs including, e.g., costs of restoring the object’s serviceability (in other words repair costs, corrective maintenance costs), penalties resulting from the object’s unavailability for operation and the loss of revenues caused by the unplanned interruption of operation;

preventive maintenance costs, which include the costs of performing preventive maintenance services (inspections and the related repairs) and also, if necessary, the loss of revenues resulting from the planned interruption of operation.

The exploitation costs of a technical object, along with the costs of its acquisition and decommissioning, represent life-cycle costs (Legutko, 2004; PN-EN 60300-3-3, 2001; Woropay, 1996). Experience shows that exploitation costs are 2 to 20 times higher than the acquisition costs of the object (Kowalski et al., 2007; Ryan, 1968). Therefore, the exploitation costs should remain the primary subject of analysis while performing a comparative assessment of the alternative purchase solutions.

The article addresses the role of operational costs in the analysis of life-cycle cost (LCC). It discusses methods for estimating operational costs of technical objects, most commonly used in practice and suggested in the subject literature. Also, it presents a method for forecasting the operational costs of a technical object. Single-mode railbuses operated by one of the regional railway companies providing passenger transport were chosen as the research object. The method was tested to verify its practical applicability when estimating the operational costs of an object.

Literature review

The conducted analysis of the available publications, discussing the LCC analysis, shows that:

the basic components of operational costs cover the costs of energy consumption (e.g., fuel, diesel) and also the labour costs of employees using the object;

the basic parameters

The cost parameter is defined by mathematical formulas containing functions and constant values. The parameter cannot represent the sum of other costs (Szkoda, 2007).

of operational costs include the costs of human labour per unit of time, the number of people using the technical object, the purchase price of an energy unit and energy consumption per time unit;

the average unit parameter values resulting from the analysis of previous years are adopted in the calculation of operational costs;

operational costs depend on the value of the technical object readiness index;

operational costs are calculated on an annual basis and next multiplied by the number of years of the object operation or for the entire life cycle of the technical object;

the operational costs of a technical object are estimated based on constant prices or a discount coefficient, which considers the fluctuations of money value over time.

Operational costs, in simplified terms, can be calculated as the sum of values of two components, i.e., energy consumption costs (e.g. fuel, diesel) and the costs of human labour: ku¯=kze¯+kup¯\overline {{k_u}} = \overline {{k_{ze}}} + \overline {k_u^p} while: kze¯=kenz¯zen¯\overline {{k_{ze}}} = \overline {k_{en}^z} \cdot \overline {{z_{en}}} where:

ku¯\overline {{k_u}} — average cost of a technical object operation per time unit,

kze¯\overline {{k_{ze}}} — average energy cost per time unit,

kup¯\overline {k_u^p} — average labour cost of the personnel using the technical object per time unit,

kenz¯\overline {k_{en}^z} — average purchase price of energy unit,

zen¯\overline {{z_{en}}} — average energy consumption per time unit.

Kumar, Chattopadhyay and Pannu (2004) proposed to consider the readiness of a technical object in addition to specifying the aforementioned two components of the operational cost. The formula for operational cost estimation in the n-th time unit should have the following form: KU=WGCEku¯{K_U} = {W_G} \cdot {C_E} \cdot \overline {{k_u}} while: WG=cnzm¯cnzm¯+cnzp¯{W_G} = {{\overline {c_{nz}^m}} \over {\overline {c_{nz}^m} + \overline {c_{nz}^p}}} where:

KU — operational costs of a technical object in the n-th time unit,

WG — the technical object readiness index,

CE — exploitation period (service life) of a technical object per n-th time unit; exploitation period can be expressed by, e.g., mileage, number of hours of operation, calendar time, clock time, etc.,

cnzm¯\overline {c_{nz}^m} — average time between the failure of a technical object caused by corrective or preventive maintenance,

cnzp¯\overline {c_{nz}^p} — average downtime of the object operation caused by the need to perform corrective or preventive services.

KU=KZWGKU = KZ \cdot {W_G} while: WG=cokd¯cokd¯+cokp¯{W_G} = {{\overline {c_{ok}^d}} \over {\overline {c_{ok}^d} + \overline {c_{ok}^p}}} where:

KU — operational costs incurred during the life cycle of the technical object,

KZ — purchase price of the object,

cokd¯\overline {c_{ok}^d} — average time of operation till failure,

cokp¯\overline {c_{ok}^p} — average downtime of the object caused by its failure.

It is worth adding at this point that — depending on the type of an object — the cost of energy consumption is measured in different ways. For example, the standards O-CR-001 (Norsok Standard, 1996a) and O-CR-002 (Norsok Standard, 1996b) provide formulas for calculating energy by the devices in which the power demand is constant and independent of production, whereas the studies by Dhillon (1989) and Monteith (1984) present the cost estimation method of fuel consumption for an aircraft and an engine.

In many scientific papers and publications addressing the LCC analysis (e.g., Bernat & Zieliński, 2006; Bonca & Sieniuc, 2005a, 2005b; Cieślak, 2008; Koniszewski et al., 2009; Palka-Wyżykowska, 2008; Szul, 2011; Hydraulic Institute or Europump, 2001; Świderski, 2003; Kutut et al., 2008; Man et al., 2011) the exploitation cost is the same as the cost of energy. In the LCC analysis, these costs are perceived as fixed over time. In fact, however, their level depends, e.g., on the method of using technical objects and the habits of their users, as well as energy prices within the calculation period. Energy costs in the LCC analysis are determined at the end of each year’s forecast. These costs are either discounted (Bernat & Zieliński, 2006; Cieślak, 2008; Koniszewski et al., 2009; Szul, 2011; Pasierb et al., 2008; Świderski, 2003; Hydraulic Institute or Europump, 2001) or not (Bonca & Sieniuc, 2005a, 2005b; Palka-Wyżykowska, 2008; Pasierb et al., 2008) against the base year of the analysis.

Methodological approach

The conducted investigation, which followed after collecting and organising information on cost estimation of a technical object operation, resulted in a proposal to use the calculation procedure consisting of eight stages for cost forecasting (Fig. 1). The method estimates cost parameters, using the central tendency values and the values of lower and upper quantiles, which allows estimating costs in three variants: the expected (e.g., modal), the optimistic and the pessimistic.

Fig. 1

Algorithm followed in the method for forecasting the costs of a technical object operation

The procedure starts with defining the division structure of an operational cost, i.e. the cost components and the included parameters. The operational cost structure is described by the following correlation: KU=KA,KABKU = \left\langle {{K_A},\,{K_{AB}}} \right\rangle where:

KA — the set of operational cost components,

Kaa-th operational cost component, where a = 1,2, …, A,

KAB — the set of parameters assigned to the set of operational cost components,

Kabb-th parameter of a-th operational cost component, where b = 1,2, …, B.

The second stage consists of defining the same length (span) of time intervals, Δt1 = Δt2 = . . .= ΔtD, while d = 1,2, …, D, where d stands for the time interval number, whereas D represents the number of intervals. The range span is the difference between the upper tgdt_g^d and lower tgdt_g^d time interval value. The range is bounded top, with the upper limit in the given range being the same as the lower limit of the next range.

The third stage of the method covers calculating the mean value of the b-th parameter included in the a-th operational cost components for the d-th time interval. The estimated mean values of the parameter are assigned at the upper limits of the d-th time interval, i.e., tgdt_g^d .

The fourth stage of the method is focused on analysing the correlation occurrence between time — Y and the mean values of the b-th parameter of the a-th operational cost component calculated in the d-th time intervals — X. For this purpose, the correlation coefficient estimator ρ can be used between the two examined attributes in the population, i.e., the correlation coefficient from the r sample (Greń, 1982): r=Σd=1D(xd-x¯)(yd-y¯)Σd=1D(xd-x¯)Σd=1D(yd-y¯)r = {{\Sigma _{d = 1}^D({x^d} - \bar x) \cdot ({y^d} - \bar y)} \over {\sqrt {\Sigma _{d = 1}^D({x^d} - \bar x) \cdot \Sigma _{d = 1}^D({y^d} - \bar y)}}} where:

xdX variable value, i.e. mean value of the b-th parameter of a-th operational cost component in the d-th time interval,

ydY variable value, i.e. time reflected by the upper limit of the d-th time interval tgdt_g^d ,

— arithmetic mean X variable,

ȳ — arithmetic mean of Y variable,

D — number of observations, the same as the number of time intervals.

To verify the significance of the correlation coefficient, the hypothesis that X and Y variables are not correlated should be checked, i.e., the null hypothesis H0: ρ = 0, against the alternative hypothesis H1: ρ ≠ 0. Student’s t-distribution for the predetermined α significance level and for D − 2 degrees of freedom shows t critical value, so that P{|t| ≥ t} =∝. If the comparison of t value is calculated based on formula 9(9), i.e., t(,n-2)=r1-r2D-2{t_{(\propto,n - 2)}} = {r \over {\sqrt {1 - {r^2}}}} \cdot \sqrt {D - 2} with t critical value results in |t| ≥ t inequality, then H0 hypothesis about the absence of correlation between the variables has to be rejected. However, when |t| < t, there are no grounds to reject the H0 hypothesis, that X and Y variables are uncorrelated.

In the case when it is unfounded to reject the H0 hypothesis, the theoretical distribution functions (stage five) have to fit the mean values of the b-th parameters of the a-th operational cost components defined for the d-th time intervals. For the probability distribution fitting of X variable, any central tendency value should be determined, i.e., the expected value, modal value or median as well as the lower F(xq) and upper quantile F(x1−q). q order quantile for 0 < q < 1 takes xq number, which meets the condition: F(xq)=-xqf(x)dx=qF({x_q}) = \int_{- \infty}^{{x_q}} {f(x)dx = q} where:

F(x) — cumulative distribution function of X random variable,

f(x) — probability density function of X variable probability.

If there are grounds to reject H0 hypothesis, the trend line (stage 6a) should fit the mean values of the b-th parameter defined for the d-th intervals. Stage 6b consists in examining the model compliance with empirical data using R2 coefficient of determination (Dittman, 2003): R2=Σt=1z(xt^-x¯)2Σt=1z(xt-x¯)2{R^2} = {{\Sigma _{t = 1}^z{{(\widehat {{x_t}} - \bar x)}^2}} \over {\Sigma _{t = 1}^z{{({x_t} - \bar x)}^2}}} where:

xt — cost parameter value in t period,

xt^\widehat {{x_t}} — theoretical cost parameter value in t period,

— mean value of cost parameter in z time series.

To verify the coefficient significance, statistics F should be used (Dittman, 2003): F=R21-R2D-k-1kF = {{{R^2}} \over {1 - {R^2}}} \cdot {{D - k - 1} \over k} where:

D — number of the dependent variable observations (the same as the number of classes),

k — number of predictor variables in the model excluding the variable with the intercept,

which has Fisher–Snedecor F distribution with k1 = k and k2 = Dk − 1 degrees of freedom, whether the model is inconsistent with the empirical data, i.e., H0: R2 = 0 null hypothesis against the alternative H1: R2 ≠ 0 hypothesis. If F value is smaller than F from Fisher-Snedecor F distribution tables for the adopted ∝ significance level and also for k1 = k and k2 = Dk − 1 degrees of freedom, there are no grounds to reject the H0 hypothesis, which means that the coefficient of determination is not significantly different from zero — the model fit to empirical data is far too weak. In this case, such a trend model of the analysed parameter should be found, for which F statistics can show a correlation occurrence between the data (stage 6a). However, if the coefficient of determination is statistically different from zero, the lower F(xq) and upper quantile values F(x1−q) of the b-th parameter of the a-th operational cost component for each Δt time interval should be determined (stage 6c). Next, in the course of stage 6d, the correlation occurrence between Y time and the defined lower F(xq) and upper quantile values F(x1−q) should be analysed using a correlation coefficient estimator. The hypothesis can be verified using Student’s t-distribution with D − 2 degrees of freedom. If there are no grounds to reject the H0 hypothesis, the theoretical distribution function has to fit the quantile values of the b-th parameter of the a-th operational cost component (stage 6h). For the fitted probability distribution of Xq variable, any central tendency value should be defined. However, if there are grounds to reject the H0 hypothesis, the theoretical distribution functions have to fit the quantile values of the b-th parameter of the a-th operational cost component (stage 6e) and the analysis (stage 6f) — using R2 coefficient of determination — of the developed model compliance with empirical data has to be conducted. The assessment of correlations is performed by testing H0 : R2 = 0 and H1 : R2 ≠ 0 hypotheses. The hypothesis can be verified using statistics which has Fisher–Snedecor F distribution with k1 = k and k2 = Dk − 1 degrees of freedom. If there are grounds to adopt H0 : R2 = 0 null hypothesis, then such a trend model of the analysed parameter should be defined, for which F statistics will determine the correlation occurrence between the data (stage 6e). In the case when R2 coefficient of determination is statistically different from zero both in stage 6b and 6f, then in the course of stage 6g, the future value of the b-th parameter of the a-th cost component is determined. This value is obtained by extrapolating the trend function, i.e., by substituting time variable in the model with t moment number or T period for which the forecast is prepared.

The seventh stage consists of the estimation of cost components. The estimation of cost components is based on analytical expressions defined in the second part of the article or by the researcher. The cost component value estimated for the entire life cycle of the T technical object, for which at least one of the parameters remains time-dependent is equal to: Ka=t=1TKat{K_a} = \Sigma_{t = 1}^T {{K_{{a_t}}}}

Whereas the cost component value for the T entire life cycle of the technical object, for which none of the parameters depends on time should be determined based on the following correlation: Ka=Kat=1T{K_a} = {K_{{a_{t = 1}}}} \cdot T

Stage eight is focused on summing up the cost components included in the operational cost: KU=a=1AKaKU = \Sigma_{a = 1}^A {{K_a}}

Conducting the research and results
Object and period

The method for forecasting the costs of a technical object operation was made for eight single-mode railbuses of type X (manufactured by the same producer), which are a homogeneous set of objects in terms of construction solutions. The railbuses are owned by the Lower Silesia Marshal’s Office and operated by a regional rail carrier. Because of a signed statement regarding data confidentiality, the name of the rail carrier could not be disclosed, and the marks (inventory numbers) of vehicles had to be changed.

Some analysed railbuses were taken by the analysed company from another railway company, and others were new, bought by the Regional Government and rented to the analysed company. The vehicles were in possession of the analysed company at different times of their life, as illustrated in Fig. 2.

Fig. 2

Schedule of the performed research analysis

The period of research analysis encompassed 42 months of rail carrier performance, from December 2013 to June 2017.

The analysis period addressed the events and activities recorded from the 1st till the 50th month of the railbus exploitation. The exploitation time covered by the study was not identical for all analysed railbuses, i.e., for buses 1, 2 and 3 determining the operational cost parameters was possible from the 9th till the 50th month of exploitation. However, for the buses No. 4 and 5, it was possible from the 1st till the 19th month of exploitation, whereas for other objects from the 1st till the 16th, 13th and 12th month, i.e., for buses 6, 7 and 8, respectively.

Assumptions

The cost components were estimated, adopting the following assumptions:

A railbus crew consists of one conductor and one driver;

The central tendency measure is the expected value of E(X) parameters;

The adopted horizon of cost forecasting is 50 months;

The exploitation month is not the same as the calendar month;

When calculating the number of days in the month of exploitation, the calendar year was considered to have 365 days;

Costs are not discounted;

The structure of operating costs consists of two components and seven cost parameters included in them (Fig. 3)

Cost components were defined based on the following formulas: K1=K1/2[(K12K13)+(K14K15)]{K_1} = {K_{1/2}} \cdot [({K_{12}} \cdot {K_{13}}) + ({K_{14}} \cdot {K_{15}})]K2=K1/2K22K23{K_2} = {K_{1/2}} \cdot {K_{22}} \cdot {K_{23}}

The accuracy degree of the operational cost forecast was measured using the ex-post relative forecast error from the formula (Cieślak, 2005): γt=KUt-KUtrzKUt100{\gamma _t} = {{K{U_t} - KU_t^{rz}} \over {K{U_t}}} \cdot 100 where:

γt — ex-post relative forecast error at the end of the Δt time interval,

KUt — forecasted operational cost value at the end of the Δt time interval,

KUtrzKU_t^{rz} — actual value of the vehicle operational costs in the Δt time interval.

Fig. 3

Structure of costs distribution of a railbus operation adopted for calculations

Application of the method for fore-casting the operational costs of technical objects

The statistical data analysis was performed using the functions and commands available in Microsoft Excel. Weibull++ application was also used, which allowed, e.g.:

developing histograms and cumulative distribution functions for random variables,

the verification of hypotheses (carried out using Spearman’s rho φ correlation coefficient) in the form of distributions of the analysed random variables,

the estimation of the unknown distribution characteristics.

For the purposes of the developed method, time series for the operational cost parameters were constructed by averaging the cost parameter per month of railbus exploitation (Fig. 4). In turn, Fig. 5 shows the course of the cumulative distribution function in the probability distribution grid for the operational cost parameters of railbuses.

Fig. 4

Data for the time series analysis covering a given operational cost parameter of railbuses: a) daily mileage of railbuses, b) salaries of conductors per kilometre of the route, c) salaries of train drivers per kilometre of the route, d) diesel consumption per kilometre of the route, and e) purchase price of a litre of diesel

Fig. 5

Distribution of operational cost parameters for test objects: a) daily mileage of railbuses, b) salaries of conductors per kilometre of the route, c) salaries of train drivers per kilometre of the route, d) diesel consumption per kilometre of the route, and e) purchase price of a litre of diesel

Fig. 6

Cumulative operational costs of railbuses in the analysed period presented as the months of exploitation

The list of parameters necessary to estimate the cost components described by formulas (16) and (17) is presented in Table 1. The analysis of the collected information shows that the operational cost parameters are not time-dependent. The analysis indicates that the distributions of daily mileage of railbuses, a train driver’s cost of work per 1 kilometre of the route, diesel consumption per kilometre of the route and the purchase price of a litre of diesel can be modelled with a normal distribution — a high value of Spearman’s rho φ correlation coefficient was received, ranging from 0.88 to 0.99. In turn, the cost of a conductor’s work per kilometre of the route can be described by a log-normal distribution (φ = 0.99). The expected value as well as F(xq) lower and F(x1−q) upper quantile for q = 0.05 were determined for the adjusted probability distributions.

Parameters of the operational cost components for time intervals presented as the months of vehicle exploitation

Parameters of the operational cost components
K1/2K12K14K22K23
Stage 4Correlation coefficient (r)−0.22−0.070.060.18−0.25
For ∝= 0,05t = −1.59p = 0.12p > ∝t = −0.51p = 0.61p > ∝t = 0.45p = 0.65p > ∝t =1.27p =0.21p > ∝t = −1.78p = 0.08p > ∝
Accepted hypothesisH0: ρ = 0H0: ρ = 0H0: ρ = 0H0: ρ = 0H0: ρ = 0
Stage 5Type of probability distributionNormalLog-normalNormalNormalNormal
Distribution matching (φ)0.970.990.990.990.88
E(X)367.851.232.074.750.58
F(x0,95)480.951.462.415.600.69
F(x0,05)254.760.021.723.910.47

The relative errors made when measuring operational costs at the end of the Δt time interval, i.e., the last period, in which the actual costs were recorded, are summarised in Table 2. The prognostic value of the described method is high, as confirmed by the calculated mean value of the relative error module. In forecasting the operational costs of railbuses, the average error was approx. 2.9%.

Relative errors in measuring operational costs of railbuses

Railbus numberLast month of the railbus exploitation tKUtrz{\bf{\it{KU}}}_{\bf{\it{t}}}^{{\bf{\it{rz}}}}KUtγtMean relative error
15033793573340998−1.1%2.9%
250315651533409985.5%
35034163623340998−2.3%
419122647212695793.4%
51912769961269579−0.58%
61611409011069119−6.7%
713873708868659−0.58%
812825694801839−3.0%

The list of parameters necessary to estimate the cost components described by formulas (16) and (17) is presented in Table 1. The analysis of the collected information shows that the operational cost parameters are not time-dependent. The analysis indicates that the distributions of daily mileage of railbuses, a train driver’s cost of work per 1 kilometre of the route, diesel consumption per kilometre of the route and the purchase price of a litre of diesel can be modelled with a normal distribution — a high value of Spearman’s rho φ correlation coefficient was received, ranging from 0.88 to 0.99. In turn, the cost of a conductor’s work per kilometre of the route can be described by a log-normal distribution (φ = 0.99). The expected value as well as F(xq) lower and F(x1−q) upper quantile for q=0.05 were determined for the adjusted probability distributions.

The relative errors made when measuring operational costs at the end of the Δt time interval, i.e., the last period, in which the actual costs were recorded, are summarised in Table 2. The prognostic value of the described method is high, as confirmed by the calculated mean value of the relative error module. In forecasting the operational costs of railbuses, the average error was approx. 2.9%.

Conclusions

The article discusses the method aimed at fore-casting operational costs of technical objects. The presented method allows estimating operational costs in the adopted life-cycle of a technical object. The estimation of costs within three variants, i.e., the expected variant (e.g., modal), the optimistic variant and the pessimistic variant, allows determining the cost range of a technical object operation. It is a universal method, as it can be used for any technical object (provided that the historical data related to the operation of identical objects or homogeneous objects, in terms of their structural solutions, were collected). In addition, this method allows capturing the variability of maintenance costs over time, arising from the gradual changes in object parameters, resulting from technical wear, by examining the correlations of technical parameters such as, e.g., diesel consumption. It should be noted that in the presented method, the level of costs depends on, e.g.:

the number of components adopted for analysis and the cost parameters identified within them;

the adopted exploitation time unit;

the adopted central tendency measure and the confidence interval in the calculations of quantile values.

The analysis of the compliance between forecasted operational costs and the actual costs showed a high correlation, as evidenced by the level of estimated relative errors. Therefore, the method, which was approached as the possibility of its application to estimate operational costs during future periods, has a relatively high prognostic value.

The presented method can also become the basis for estimating total operational costs, which remain an important cost component, considered when assessing the profitability of purchasing one of several competing technical objects offered by the industry. Thus, the modification of the presented method and its implementation constitute the next stage of the author’s research covering the LCC analysis.