Incorporating Lean Construction agent into the Building Standards Act: the Spanish case study


Zacytuj

Commentaries on Supreme Court's main rulings on constructive managers

No.CodesContentComments
1STS 1256/2004Constructive manager's liability regarding his actions as site managerThe lean construction specialist works directly with all other specialists and could be confused in that way.
2STS 2071/2001Constructive manager's liability as he coordinated, supervised technical matters and made decisions on site.The lean construction specialist can perform in this area.
3ATS 5879/2011Constructive manager's liability as he participated in other agent's functions.The lean construction specialist interacts with other specialists.
4STS 2676/2009Responsible as cooperative manager, or owner manager, or similarThe lean construction specialist can be included in this area, if he were part of the project from the beginning.
5STS 1726/2015Free of responsibility as cooperative manager or owner manager or similar.The lean construction specialist could be included in this area if he were part of the project from the beginning.
6STS 4524/1994Absolved of all responsibility for construction defects.The lean construction specialist interacts with other specialists and could initially be included in this area.
7STS 4650/1979Responsible for damages to third parties and large losses and for interrupted electric supply.The lean construction specialist interacts with other specialists and could be included in this area.
8STS 5950/2009Responsible for damages in the delayed completion date of the apartments, and all those agents who participated in the project should be sued equally, in order to correct all damages.The lean construction specialist interacts with other specialists and could be included in this area.
9STS 6563/2011Responsibility for damages to third parties for unexpected settlement of the neighboring building, of one or more owners, or similarThe lean construction specialist interacts with other specialists and could be included in this area.
10STS 7941/2006Responsibility for latent defect or construction defects.The lean construction specialist interacts with other specialists and could be included in this area.
11STS 8112/2007Responsibility for damages in terms of the delay of completion date, and all parties should be equally liable pending correction of all damages.The lean construction specialist interacts with other specialists and could be included in this area.
12STS 8151/2004Responsibility for latent defect or construction defects.The lean construction specialist interacts with other specialists and could be included in this area.
13STS 8710/2007Absolved of all responsibility under the name of manager, cooperative manager, or owner manager or similar.The lean construction specialist interacts with other specialists and could be included in this area.
14ATS 756/1998Responsibility for latent defect or construction defects.The lean construction specialist interacts with other specialists and could be included in this area.
15ATS 960/2007Responsibility as cooperative manager, or owner manager or similar.The lean construction specialist interacts with other specialists and could be included in this area.
16ATS 1769/2014Responsibility for latent defect or construction defects.The lean construction specialist interacts with other specialists and could be included in this area.
17ATS 4007/2014Responsibility as cooperative manager, or owner manager or similar.The lean construction specialist interacts with other specialists and could be included in this area.