Determination of construction process duration based on labor productivity estimation: A case study
et
20 nov. 2021
À propos de cet article
Catégorie d'article: Research Paper
Publié en ligne: 20 nov. 2021
Pages: 2521 - 2538
Reçu: 21 mars 2021
Accepté: 30 sept. 2021
DOI: https://doi.org/10.2478/otmcj-2021-0031
Mots clés
© 2021 Darja Kubečková et al., published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Fig. 1

Fig. 2

Plastering works – Distribution of number of plasterers in work queue no_1
1 | 8 | 87.6 | 1,752 |
2 | 8 | 87.6 | 1,752 |
3 | – | – | – |
4 | – | – | – |
5 | – | – | – |
6 | – | – | – |
7 | – | – | – |
ς | 16 | 175.2 | 3,504 |
Plastering works SO J 34
Worker no. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
Performance/shift | 12 | 11 | 10 | 12 | 11 | 13 | 12 | 11 | 10 | 12 | 11 | 10 | 13 | 10 | 12 | 11 |
Worker no. | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 |
Performance/shift | 12 | 11 | 11 | 12 | 11 | 13 | 12 | 11 | 12 | 12 | 11 | 12 | 13 | 12 | 10 | 12 |
Calculation of observed value XOBS – originally wrongly numbered 2
10 | 1 | 0 | 0.063 | 0.036 | 0.027 | 0.036 | 0.036 | ||
10 | 2 | 0.063 | 0.125 | 0.036 | 0.089 | −0.027 | 0.089 | ||
11 | 9 | 0.5 | 0.563 | 0.274 | 0.289 | −0.226 | 0.289 | ||
12 | 10 | 0.563 | 0.625 | 0.726 | −0.101 | 0.163 | 0.163 | ||
12 | 11 | 0.625 | 0.688 | 0.726 | −0.038 | 0.101 | 0.101 | ||
12 | 12 | 0.688 | 0.75 | 0.726 | 0.024 | 0.038 | 0.038 | ||
12 | 13 | 0.75 | 0.813 | 0.726 | 0.087 | −0.024 | 0.087 | ||
12 | 14 | 0.813 | 0.875 | 0.726 | 0.149 | −0.087 | 0.149 | ||
13 | 15 | 0.875 | 0.938 | 0.964 | −0.026 | 0.089 | 0.089 | ||
13 | 16 | 0.938 | 1 | 0.964 | 0.036 | 0.026 | 0.036 |