Determination of construction process duration based on labor productivity estimation: A case study


Cite

Fig. 1

Type of above-ground floor of building J1–J2.
Type of above-ground floor of building J1–J2.

Fig. 2

Comparison of process duration.
Comparison of process duration.

Plastering works – Distribution of number of plasterers in work queue no.1

Floor No. of plasterers Overall performance plan m2/sm Overall performance plan m2/month
1 8 87.6 1,752
2 8 87.6 1,752
3
4
5
6
7
ς 16 175.2 3,504

Plastering works SO J 34

Worker no. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Performance/shift 12 11 10 12 11 13 12 11 10 12 11 10 13 10 12 11
Worker no. 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Performance/shift 12 11 11 12 11 13 12 11 12 12 11 12 13 12 10 12

Calculation of observed value XOBS – originally wrongly numbered 2

Ordered Series (i) (í−1)/n í/n F(x) D pro D pro D

Values x i/n (í−1)/n
10 1 0 0.063 0.036 0.027 0.036 0.036
10 2 0.063 0.125 0.036 0.089 −0.027 0.089
11 9 0.5 0.563 0.274 0.289 −0.226 0.289
12 10 0.563 0.625 0.726 −0.101 0.163 0.163
12 11 0.625 0.688 0.726 −0.038 0.101 0.101
12 12 0.688 0.75 0.726 0.024 0.038 0.038
12 13 0.75 0.813 0.726 0.087 −0.024 0.087
12 14 0.813 0.875 0.726 0.149 −0.087 0.149
13 15 0.875 0.938 0.964 −0.026 0.089 0.089
13 16 0.938 1 0.964 0.036 0.026 0.036