Cite

Characteristics of case projects

DescriptionUnitValueRemark
Number of case projectsea.210
Mean, award bidU$20,916,801.39SD 31,430,304.83
Mean, project final costU$21,324,687.90SD 31,831,462.92
Mean, number of biddersea.4.28SD 2.13
Mean, CV of bids%7.42SD 4.76
Mean, project cost change%5.36SD 5.99

Comparison of means of project cost changes against the number of bidders and CV percentile

Description2-bid projects3-bid projects4-bid projects5-bid projects6-bid projects7-bid projects
50%Mean, top 50% CV,%7.614.456.754.246.397.98
Mean, bottom 50% CV,%3.666.203.913.933.035.03
p-value0.010.360.160.870.150.24
40%Mean, top 40% CV,%7.644.626.524.266.098.94
Mean, bottom 40% CV,%3.285.473.244.243.134.50
p-value0.020.700.120.990.330.14
30%Mean, top 30% CV,%6.984.156.974.757.279.24
Mean, bottom 30% CV,%3.365.633.205.272.942.50
p-value0.040.600.150.870.270.05
20%Mean, top 20% CV,%6.114.768.623.183.996.19
Mean, bottom 20% CV,%3.615.612.976.344.002.19
p-value0.310.840.150.350.990.01
10%Mean, top 10% CV,%7.598.0412.672.132.807.30
Mean, bottom 10% CV,%4.228.543.978.582.951.17
p-value0.440.950.260.550.960.02

Summary of analysis results

DescriptionUnitValue
Number of case projectsea.210
Mean, number of bidders (SD)ea.4.28 (2.13)
Mean, CV (SD)%7.42 (4.76)
Mean, project cost change (SD)%5.36 (5.99)
Mean, project cost change, above-average CV (SD) [A]%6.49 (6.73)
Mean, project cost change, below-average CV (SD) [B]%4.24 (4.92)
p-value between [A] and [B]0.01
eISSN:
1847-6228
Idioma:
Inglés
Calendario de la edición:
Volume Open
Temas de la revista:
Engineering, Introductions and Overviews, other