According to Polish law, it is prohibited to perform excavations or locate buildings closer than 50 m from the embankment. In order to obtain exemption from this ban, filtration and stability analysis of the embankment and excavation in the flood conditions have to be performed. This paper presents results of the numerical investigations on interactions between excavations and embankment. Complex nature of the problem is presented. Methodology of numerical simulations and real case examples are described.