Decision-support modelling tool for contractor-to-project assignment and project management
Jun 12, 2025
About this article
Article Category: Research Paper
Published Online: Jun 12, 2025
Page range: 96 - 109
Received: Nov 21, 2024
Accepted: Feb 10, 2025
DOI: https://doi.org/10.2478/otmcj-2025-0006
Keywords
© 2025 Hakob G. Avetisyan, published by Sciendo
This work is licensed under the Creative Commons Attribution 4.0 International License.
Fig. 1:

Fig. 2:

Fig. 3:

j_otmcj-2025-0006_utab_001
= 0.543 | |
= 0.078 | |
= 0.090 | |
= 0.109 | |
= 0.181 |
AHP attribute pairwise comparison normalised data with SPM setup_
Attributes | A | B | C | D | E |
---|---|---|---|---|---|
A | 0.543 | 0.543 | 0.543 | 0.543 | 0.543 |
B | 0.078 | 0.078 | 0.078 | 0.078 | 0.078 |
C | 0.090 | 0.090 | 0.090 | 0.090 | 0.090 |
D | 0.109 | 0.109 | 0.109 | 0.109 | 0.109 |
E | 0.181 | 0.181 | 0.181 | 0.181 | 0.181 |
Contractors K and J payoff data_
J | ||||
---|---|---|---|---|
K | Alpha values | Project 1 | Project 2 | Project 3 |
Project 1 | 0.349/0.411 | 0.349/0.340 | 0.349/0.249 | |
Project 2 | 0.440/0.411 | 0.440/0.340 | 0.440/0.249 | |
Project 3 | 0.211/0.411 | 0.211/0.340 | 0.211/0.249 |
Contractor B’s valuation of projects_
Project J | Alpha |
---|---|
Project 1 | 0.37 |
Project 2 | 0.52 |
Project 3 | 0.11 |
AHP attribute pairwise comparison table also presented as a matrix M for calculations_
Attributes | A | B | C | D | E |
---|---|---|---|---|---|
A | 1.00 | 7.00 | 6.00 | 5.00 | 3.00 |
B | 3.00 | 1.00 | 5.00 | 7.00 | 4.00 |
C | 2.00 | 0.20 | 1.00 | 3.00 | 1.00 |
D | 0.20 | 1.00 | 0.30 | 1.00 | 0.30 |
E | 0.20 | 0.20 | 1.00 | 4.00 | 1.00 |
AHP attribute pairwise comparison with SPM setup_
Attributes | A | B | C | D | E |
---|---|---|---|---|---|
A | 1.00 | 7.00 | 6.00 | 5.00 | 3.00 |
B | 0.10 | 1.00 | 0.90 | 0.70 | 0.40 |
C | 0.20 | 1.20 | 1.00 | 0.80 | 0.50 |
D | 0.20 | 1.40 | 1.20 | 1.00 | 0.60 |
E | 0.30 | 2.30 | 2.00 | 1.70 | 1.00 |
Pairwise project-to-project comparison per attribute A_
Projects | 1 | 2 | 3 |
---|---|---|---|
1 | 1.00 | 0.33 | 1.00 |
2 | 0.10 | 1.00 | 2.00 |
3 | 1.00 | 0.50 | 1.00 |
Contractor C’s valuation of projects_
Project J | Alpha |
---|---|
Project 1 | 0.18 |
Project 2 | 0.41 |
Project 3 | 0.41 |
Contractors A, B, and C (third number under each project) payoff data per project_
B | |||
---|---|---|---|
A | Alpha values | Project 1 | Project 2 |
Project 1 | 0.45/0.37/0.18 | 0.45/0.52/0.41 | |
Project 2 | 0.27/0.37/0.18 | 0.27/0.52/0.41 |
Final output from SPM_
Weights i/project J | 0.543 | 0.078 | 0.090 | 0.109 | 0.181 | Alpha |
---|---|---|---|---|---|---|
Project 1 | 0.210 | 0.120 | 0.500 | 0.630 | 0.620 | 0.349 |
Project 2 | 0.550 | 0.550 | 0.250 | 0.300 | 0.240 | 0.440 |
Project 3 | 0.240 | 0.330 | 0.250 | 0.070 | 0.140 | 0.211 |
Contractor J’s valuation of projects_
Project j | Alpha |
---|---|
Project 1 | 0.411 |
Project 2 | 0.340 |
Project 3 | 0.249 |
Contractors K and J reduced payoff data_
J | |||
---|---|---|---|
K | Alpha values | Project 1 | Project 2 |
Project 1 | 0.349/0.411 | 0.349/0.340 | |
Project 2 | 0.440/0.411 | 0.440/0.340 |
a, m, and b values to estimate comparison values for attribute A to B, C, and D_
Attributes ratio | Pairwise comparison value | |||
---|---|---|---|---|
5.00 | 7.00 | 9.00 | A/B | 7.00 |
5.00 | 6.00 | 7.00 | A/C | 6.00 |
4.00 | 5.00 | 6.00 | A/D | 5.00 |
1.00 | 3.00 | 5.00 | A/E | 3.00 |
Contractor A’s valuation of projects_
Project J | Alpha |
---|---|
Project 1 | 0.45 |
Project 2 | 0.27 |
Project 3 | 0.28 |
Normalised pairwise project-to-project comparison per attribute A_
Projects | 1 | 2 | 3 |
---|---|---|---|
1 | 0.20 | 0.180 | 0.250 |
2 | 0.60 | 0.550 | 0.500 |
3 | 0.20 | 0.270 | 0.250 |