Modeling Effective Budgeting and Production For Sustainable Competitive Advantage: Evidence from Kufa Cement Factory, Iraq

, ,  and   
Dec 17, 2024

Cite
Download Cover

Figure 1.

Cleaner production practices
(Source: Authors’ own research)
Cleaner production practices (Source: Authors’ own research)

Figure 2.

The benefits of CP technique and production processes
(Source: Authors’ own research)
The benefits of CP technique and production processes (Source: Authors’ own research)

Figure 3.

Sustainable budgeting
(Source: Authors’ own research)
Sustainable budgeting (Source: Authors’ own research)

Figure 4.

Industrial process modification and introduction of advanced systems
(Source: Authors’ own research)
Industrial process modification and introduction of advanced systems (Source: Authors’ own research)

Time vectors for the activities of the rubber conveyor department events (Source: Authors’ own research)

Activities/events Receipt of the stone/min Stone transfer/min Stone count/min Total/min
Production 0.5 0.5 0.4 1.4
Mechanical maintenance 2 8 3 13
Electrical maintenance 0.7 1 0.6 2.3

Total planned costs for the product (Source: Authors’ own research)

Department Amount
The total planned cost of the quarry department 12,773 dinars/ton
The total planned cost of the rubber conveyor department 3399 dinars/ton
The total planned cost of the raw materials mills department 16,451 dinars/ton
The total planned cost of the department of furnace 26,207 dinars/ton
The total planned cost of the cement mills division 15,650 dinars/ton
The total planned cost of the packing department 8623 dinars/ton
Total planned costs for the product 83,103 dinars/ton

The planned cost of the quarry department (Source: Authors’ own research)

Activity Amount of time required for activities/min Cost per unit time Planned costs for activities
Production 7 541 3787
Mechanical maintenance 14 481 6734
Electrical maintenance 4 488 1952
The breaker 1 300 300
Total 26 1810 12,773

Time drivers for the events of the packing department activities (Source: Authors’ own research)

Activities/events Receipt of clinker/min Mixing clinker with gypsum/min Cement crushing and grinding/min Total/min
Production 1.25 1.75 2 5
Mechanical maintenance 2 7 2 11
Electrical maintenance 0.75 1.5 1.25 3.5
Precipitators 0 1.75 2 3.75

Time confrontations for the events of the activities of the cement mills department (Source: Authors’ own research)

Activities/events Conversion of cement to silo Bagging of cement Transportation of cement to suppliers Total
Production 0.4 0.6 3 4
Mechanical maintenance 1 1 2 4
Electrical maintenance 0.4 0.4 0.5 1.3

Time vectors for the events of the raw materials mills department activities (Source: Authors’ own research)

Activities/events Receipt of raw materials/min Mixing and grinding of materials/min Putty transfer/min Total/min
Production 0.5 1.6 0.4 2.5
Mechanical maintenance 3 9 2 14
Electrical maintenance 0.75 1 0.5 2.25
Water station 0.75 0.75 0 1.5

Time vectors for the events of the quarry department activities (Source: Authors’ own research)

Activities/events Cover dust detection/min Crushing and conveying of stone/min Drying and compaction of the stone/min Crushing and conveying of stone to the conveyor/min Total/min
Production 5 1.5 0.5 0 7
Mechanical maintenance 2 4 2 6 14
Electrical maintenance 0.5 1 0.5 2 4
The breaker 0 0 0 1 1

The total planned cost according to the practical capacity of the quarry department (Source: Authors’ own research)

Activity Amount of time required for activities/min (1)a Planned costs for activities (2)a Production quantity/ton (3) Total working energy per minute (1 × 3) The total planned cost according to the practical energy in dinars (2 × 3)
Production 7 3787 657,310 4,601,170 2,489,232,970
Mechanical maintenance 14 6734 657,310 9,202,340 4,426,325,540
Electrical maintenance 4 1952 657,310 2,629,240 1,283,069,120
The breaker 1 300 657,310 657,310 197,193,000
Total 26 12,773 657,310 17,090,060 8,395,820,630

Theoretical and practical capacity of the activities – Quarry department (Source: Authors’ own research)

Activity The number of workers (worker) The number of days (day) Work hours (hours) Theoretical energy (minutes) Practical energy (minutes)
Production 65 22 8 8,236,800 6,589,440
Mechanical maintenance 64 22 8 8,110,080 6,488,064
Electrical maintenance 18 22 8 2,280,960 1,824,768
Crusher 44 22 8 5,575,680 4,460,544

Planned costs for the production department for 2022 AD (Source: Authors’ own research)

Production department Activity Direct costs Indirect costs Total cost of the activity
Quarry Production 2,344,056,878 1,220,311,122 3,564,368,001
Mechanical maintenance 2,051,049,769 1,067,772,232 3,118,822,001
Electrical maintenance 586,014,220 305,077,781 891,092,000
The breaker 879,021,329 457,616,671 1,336,638,000
Total costs 5,860,142,196 3,050,777,806 8,910,920,002
Rubber conveyor Production 1,144,048,606 0 1,144,048,606
Mechanical maintenance 1,016,932,094 0 1,016,932,094
Electrical maintenance 381,349,535 0 381,349,535
Total costs 2,542,330,236 0 2,542,330,236
Raw material mills Production 4,310,235,864 1,275,830,474 5,586,066,338
Mechanical maintenance 3,771,456,381 1,116,351,664 4,887,808,045
Electrical maintenance 1,077,558,966 318,957,618 1,396,516,584
Water station 1,616,338,449 478,436,428 2,094,774,877
Total costs 10,775,589,660 3,189,576,184 13,965,165,844
Ovens department Production 9,682,351,565 1,420,061,194 11,102,412,759
Mechanical maintenance 8,472,057,620 1,242,553,544 9,714,611,164
Electrical maintenance 2,420,587,891 355,015,298 2,775,603,190
Precipitators 3,630,881,837 532,522,948 4,163,404,785
Total costs 24,205,878,913 3,550,152,984 27,756,031,897
Cement mills Production 2,968,215,208 1,019,060,166 3,987,275,374
Mechanical maintenance 2,597,188,307 891,677,645 3,488,865,952
Electrical maintenance 742,053,802 254,765,041 996,818,843
Precipitators 1,113,080,703 382,147,562 1,495,228,265
Total costs 7,420,538,020 2,547,650,414 9,968,188,434
Packing Production 2,540,433,357 648,577,556 3,189,010,913
Mechanical maintenance 2,258,162,984 576,513,383 2,834,676,367
Electrical maintenance 846,811,119 216,192,519 1,063,003,638
Total costs 5,645,407,460 1,441,283,458 7,086,690,918
The total costs 56,449,886,485 13,779,440,846 70,229,327,331

Planned final product cost per ton (Source: Authors’ own research)

Statement Details Total
Total planned production costs: "The planned production costs are based on the expected production quantity for 2022 and according to table (13)"
Planned costs of production 83,103 dinars/ton × 1,000,000 tons/year 83,103,000,000
Combined: The added costs “represent additional costs for the development of a production line and replacement of new equipment and devices”
Introducing a new production line 1,110,000,0001
Equipping mechanical precipitators 20,000,0002
Steps switch innovation 5,000,0003
Total costs added --- 1,135,000,000
Subtracted: Excluded costs “represent financial savings to avoid the costs of sediment disposal and recycling of raw materials. And the cost differences of switching from one type of fuel to another, as well as avoiding the costs of obsolete devices”
Reuse/recycle CKD material 1,306,934,3563
Substitution of fuel from oil to gas 19,250,000,0004
Replacing obsolete devices 474,000,0005
Total costs excluded --- (21,030,934,356)
Planned final costs of production --- 63,207,065,644
Planned final product cost per ton 63,207,065,644 dinars/1,000,000 tons 63,207 dinars/ton

Planned unit time cost for production departments (Source: Authors’ own research)

Production department Activity The total cost of the activity Practical energy of activity/minute Activity time unit cost (dinar/min)
Quarry Production 3,564,368,001 6,589,440 541
Mechanical maintenance 3,118,822,001 6,488,064 481
Electrical maintenance 891,092,000 1,824,768 488
The breaker 1,336,638,000 4,460,544 300
Rubber conveyor Production 1,144,048,606 3,628,800 315
Mechanical maintenance 1,016,932,094 6,082,560 167
Electrical maintenance 381,349,535 1,115,136 342
Raw material mills Production 5,586,066,338 6,386,688 875
Mechanical maintenance 4,887,808,045 6,589,440 742
Electrical maintenance 1,396,516,584 1,216,512 1148
Water station 2,094,774,877 2,433,024 861
Ovens department Production 11,102,412,759 14,192,640 782
Mechanical maintenance 9,714,611,164 11,759,616 826
Electrical maintenance 2,775,603,190 2,635,776 1053
Precipitators 4,163,404,785 3,750,912 1110
Cement mills Production 3,987,275,374 5,879,808 678
Mechanical maintenance 3,488,865,952 5,372,928 649
Electrical maintenance 996,818,843 2,433,024 410
Precipitators 1,495,228,265 1,520,640 983
Packing Production 3,189,010,913 10,441,728 305
Mechanical maintenance 2,834,676,367 1,926,144 1472
Electrical maintenance 1,063,003,638 912,384 1165

Idle energy cost and its ratio to resource groups (Source: Authors’ own research)

Resource groups (departments) The cost of idle energy Idle energy ratio
Quarry 515,099,372 5.78%
Rubber conveyor 308,133,545 12.12%
Raw material mills 3,151,759,034 22.56%
Ovens 10,529,908,728 37.93%
Cement mills -318,713,066 3.19%
Packing 1,418,706,788 20%
The total 15,604,894,401 22.21%

Time vectors for the events of the furnaces department activities (Source: Authors’ own research)

Activities/events Receipt of putty/min Maturation and burning of the putty/min Clinker leveling/min Total/min
Production 0.6 0.75 1.2 2.55
Mechanical maintenance 5 15 4 24
Electrical maintenance 0.75 1.6 0.5 2.85
Precipitators 0 1.25 0 1.25