Country | Guidelines or measure | Valid from |
Explanation of the permissible changes to contracts due to the increase in prices of materials and services | November 2021 | |
Guidelines for the implementation of procedures for the recogni- tion of price differences on the basis of construction contracts | February 2022 and April 2022 | |
Decision of the City of Belgrade | June 2022 | |
Decision of Ministry of Construction, Transport and Infrastructure | In preparation | |
Methodology for determining price differences in construction services | September 2022 | |
Application of a sliding scale | No information | |
Unconditional payment of price difference for all contracts | No information |
Channel | Pipeline diameter (mm) | Projected pipeline drop |
Length |
---|---|---|---|
DN 200 | 10.5–94.8 | 267.54 | |
DN 200 | 4.00 | 146.74 |
Channel | Base contract price (CPs) March 2021 | Index GZS-ZGIGM | New contract price (CPc) March 2022 | |
---|---|---|---|---|
40,802,91 € | 117.36 | 47,886,30 € | ||
40,002,27 € | 117.36 | 46,946,66 € |
Channel | Base contract price (CPs) March 2021 | New contract price (CPc) | March 2022 | Index |
---|---|---|---|---|
40,802,91 € | 45,681,93 € | 111.96 | ||
40,002,27 € | 50907,78 € | 127.26 |
Channel | Base contract price (CPs) March 2021 | New contract price (CPc) March 2022 | Index | |
---|---|---|---|---|
40,802,91 € | 46,298,56 € | 113.47 | ||
40,002,27 € | 49,781,79 € | 124.45 |