1 | Place first MgO board (1) | 15 | 15 | 17.25 | 12.75 |
2 | Place second MgO board (1) | 30 | 15 | 34.5 | 25.5 |
3 | Place first MgO board (2) | 15 | 15 | 17.25 | 12.75 |
4 | Place second MgO board (2) | 30 | 15 | 34.5 | 25.5 |
5 | Place insulation material (1) | 20 | 15 | 23 | 17 |
6 | Place insulation material (2) | 20 | 15 | 23 | 17 |
7 | Spray glue on MgO board (1) | 20 | 0 | 20 | 20 |
8 | Spray glue on MgO board (2) | 20 | 0 | 20 | 20 |
9 | Spray glue on insulation material (1) | 20 | 0 | 20 | 20 |
10 | Spray glue on insulation material (2) | 20 | 0 | 20 | 20 |
11 | Compress (1) | 30 | 0 | 30 | 30 |
12 | Compress (2) | 30 | 0 | 30 | 30 |
13 | Prepare timber frame | 60 | 25 | 75 | 45 |
14 | Add timber frame | 30 | 25 | 37.5 | 22.5 |
Capital cost (USD) | 10.700 | 10.700 | 10.700 | 11.500 | 19.400 |
Labor cost (USD/hr) | 100 | 200 | 200 | 300 | 300 |
Workers | 2 | 4 | 4 | 6 | 6 |
Avg. cycle time (s) | 368 | 281 | 210 | 187 | 141 |
Space required (mounted state |
91.6 | 91.6 | 91.6 | 107.6 | 107.6 |
Space req. (unmounted state) (m2) | 27.1 | 27.1 | 27.1 | 32.0 | 43.7 |
Total weight (tons) | 2.0 | 2.0 | 2.0 | 2,2 | 3.4 |
Total WS utilization | 100% | 66.6% | 89.5% | 80.7% | 88.7% |