Accès libre

Challenges in pricing preliminaries costs for contractors: An Australian case study

 et   
16 juil. 2025
À propos de cet article

Citez
Télécharger la couverture

Fig. 1:

Research methodology framework.
Research methodology framework.

Projects involved by respondents by type and value

Sub-questions Projects ($1 m – $5 m) Projects ($5 m – $20 m) Projects ($20 m – $100 m) Projects ($100 m plus) Not active in this_category of projects
Commercial all types (non-residential) 17.86 25.00 32.14 57.14 14.29
Residential work 10.71 17.86 10.71 35.71 46.43
Civil works 7.14 10.71 17.86 14.29 60.71
Refurbishment and alterations 21.43 17.86 32.14 10.71 50.00
Fit out works 25.00 21.43 32.14 10.71 42.86

Impact of building price escalation (annual %) on estimating preliminaries

Categories Mean
Supervision, site staff, admin staff, labourers, etc. 6.80
Insurances, guarantees and fees, permits, paperwork, etc. 6.40
Running costs (keeping the site going – Staff excluded) 6.00
Final cleaning & handover, commissioning (some costs at the end of the job) 5.87
Head office overheads and other costs (e.g. finance, contingency, etc.) 5.20
Establishment/disestablishment of the site (getting the site up and running and then shutting it down) 5.07

Administrative challenges in estimating preliminaries (Likert scale 1–5)

Sub-questions Mean
Understanding of the client’s main expectations, goals and specifications 3.29
Insufficient preparation time during the tender period 3.24
Costs of permits, consultants, special environmental requirements 2.94
Late responses from designers/engineers to queries raised 2.88
External factors, unions, pandemic (COVID) 2.82
Ambiguities/omissions within the tender or contract documents 2.59
Difficulty obtaining bank guarantees/insurance, financial markets 2.59
Unreliable historical cost information/subcontractor pricing 2.41
Providing for project IT services and client expectations on reporting 2.41
Lack of itemised bills of quantities for prelims 1.76

Percentage of preliminaries costs per activities (scale 0–100)

Sub-questions Mean (%)
Supervision, site staff, admin staff, labourers, etc. 44.57
Running costs (keeping the site going – Staff excluded) 12.48
Establishment and disestablishment of the site (getting the site up and running, and then shutting it down) 12.40
Insurances, guarantees and fees, permits, paperwork, etc. 11.51
Head office overheads and other costs (e.g. finance, contingency, etc.) 9.90
Final cleaning & handover, commissioning (some costs at the end of the job) 9.14

Types of schedules of preliminaries used at the estimating/tender stage

Sub-questions Total (%)
Company standard schedule (from Estimating Dept.) 65.00
Combination standard schedules and external sources e.g. quotations, pricelists 30.00
Company standard schedule (from Bid Manager/Finance Dept.) 5.00
Once off unique project schedule based on contract conditions 0.00
Industry-standard schedule based on standard proformas (ASMM, CIOB, MBA, RICS etc.) 0.00

Buildability/constructability challenges in estimating preliminaries (Likert Scale 1–5)

Field Mean
Complexity of work, e.g. site restrictions, high lifting, material handling (Cranages, Alimaks, etc.) 3.53
Different methodologies adopted within contractors and subcontractors 3.40
Access and temporary works required in each construction stage 3.27
Alternative construction methods suggested by the construction manager 3.13
Having access to existing site facilities on REFURBISHMENT projects 3.13
Difficulties in clarifying methodology and programming the works at tender time 2.87
Difficulty in predicting weather-related events with construction phases 2.73
Temporary accommodations and site amenities, including subcontractors and client needs 2.73
Regulatory issues, codes and byelaws affecting site operations (dust, noise, etc.) 2.67
Storage and parking areas 2.67
Poor responses from designers/engineers to technical queries raised 2.60

Most likely elements of preliminaries where costs increase/overrun occur, apart from any costs associated with a programme (delay or gain)

Answer %
Supervision, site staff, admin staff, labourers, etc. 43.34
Cranage, including associated labour 20.00
Final cleaning & handover, commissioning (some costs at the end of the job) 10.00
Site setup, including accommodation, hoardings, gantries, etc. 10.00
Running costs (keeping the site going – staff excluded) 6.67
Insurances, guarantees and fees, permits, paperwork, etc. 6.67
Waste during construction, rubbish removal, etc. 3.34

Most likely elements of preliminaries where cost savings occur, apart from any costs associated with a programme E(delay or gain)

Answer %
Site setup, including accommodation, hoardings, gantries, etc. 28.57
Running costs (keeping the site going – staff excluded) 23.81
Waste during construction, rubbish removal, etc. 14.29
Insurances, guarantees and fees, permits, paperwork, etc. 9.52
Supervision, site staff, admin staff, labourers, etc. 9.52
Final cleaning & handover, commissioning (some costs at the end of the job) 9.52
Cranage, including associated labour 4.76

List of suggested categories from the ANZSMM

Contractual Site conditions
1. Working hours 20. Charts, schedules
2. Rates and wages and prices of materials 21. Notice board
3. Sub-letting 22. Setting out works
4. Progress and final certificates and 23. Temporary installations
5. Variations 24. Services
6. Dates for commencement and completion 25. Telephone calls
7. Bonus for early completion 26. Temporary screens, fences, hoardings, guard rails, etc.
8. Liquidated damages 27. Temporary roads, tracks, crossing, etc.
9. Rise and fall 28. Temporary sheds, sanitary accommodation, etc.
10. Exemption from duty sales or other taxes 29. Duties and attendance
11. Issue and return of documents 30. Work outside the contract
12. Discrepancies 31. Supplied goods
13. Submission of priced bills of quantities 32. Samples
14. Contract agreement stamp 33. Testing
15. Payment of taxes 34. Advertising
16. Notices, permits, fees 35. Footpath levels
17. Liability 36. Plant equipment and attendant labour
18. Bonds, guarantees 37. Scaffolding
19. Payment of extra monies 38. Attendance
39. Protection
40. Cleaning
41. Handing over
42. Defects liability

Examples of preliminaries schedules from two Australian contractors under two different procurement methods

Case A (construction only – BB) Case B (design and build – DBB)
Labour and supervision Supervision
Site supervision Project Manager, Site Manager, Design Manager, Cost Planner, Administrator, Assistant Administrator, Design and Documentation Coordinator, Site Coordinators, Site Supervisors, Site Supervisors, Services Manager, Construction Planner, Quality Manager, Site Secretary, Tenancy Coordinator, OH&S Manager
Other Contractors Labour
As built drawings and documentation, operation and maintenance manuals Cleaning Labour and others
Insurances Fees & insurances
Authority charges Building administration fund (building control commission)
Authority service provider headwork fees and charges Hoarding & gantry permits
Professional indemnity and insurance Crossing fees
Contract works insurance Value management facilitator
Public liability insurance Consultants design fees
Professional indemnity & insurance 5% insurance bonds
Workers compensation Professional indemnity insurance
Plant & equipment Contractors’ legal fees
Bank guarantees Contractors all risk insurance
Security – Bank guarantees charges Public liability insurance
Fees and charges for the erection of scaffold systems, hoardings and gantries, the establishment of construction zones, footpath closures and tower crane loading zones Plant and equipment insurance
Building permit Warranties and guarantees
Construction industry levy Plant & equipment insurance (contractors plant)
Main site office purchases and consumables Site purchases and consumables
Loose furniture signage Safety notices/inductions/safety signage
Consumption costs Establish first aid station and consumables
Car parking Payroll delivery, postage, couriers, kitchen supplies, etc.
Plan printing Plan printing for trade packages (procurement)
Information management & document control systems Progress photographs
Courier charges Parking costs for contractor employees
Small tools Couriers
Small tools Small tools, nails and charges, etc. – (Built personnel)
Site establishment Site setup
Fencing, gantries, security gates Hoardings, fences and gates
Hoardings, fences and compounds Gantries and overhead protection – Site camp
Temporary roads tracks crossings Make good pavements
Temporary fencing or tree protection fencing Site signs
Temporary services Temporary services
Site radio communications Power consumption during construction
Temporary electrical services Water consumption during construction
Temporary hydraulic services Temporary water, sewer and fire protection – Site construction
Access lighting Temporary electrical services – Site construction
Task lighting Fire extinguishers on site
Telephone Site telephones and radios – MC personnel
ICT Site telephones and radios – Trade contractors
Site offices & accommodation Site offices & accommodation
Construction worker amenities client office Temporary site accommodation – MC & client personnel Worker amenities, change, ablution, etc. – Total workforce Site office equipment and furniture Site office running costs, consumables, etc.
General works Surveying, cleaning and protection
Survey Setout and survey – Base grids
Dilapidation survey Setout and survey – Detail trade survey
Lift opening temporary barricades Existing conditions survey
Waste management Waste minimisation programme
Safety requirement including OH&S requirements Rubbish Bin hire – Tenancy fitouts
Safety site access control Progressive cleaning – Tenancy fitouts
Dust control Cleaning
Progressive cleaning Site security
Final cleaning Protective clothing
Site security control Protection of finished works
Safety equipment Maintenance and maintenance of protection of finished works
PPE Supervision during defects liability period
Jersey barriers Defect rectification during defects liability period
Materials handling Cranage
Tower crane Fixed tower cranage for the works including crew, crane base, erection, dismantling, hire, running costs, maintenance, tower sections, landing platforms, jumping, ties, communications and sundries, etc.
Tower crane crew including driver and dogmen Trade mobile cranage including erection, dismantling, running costs, etc.
Mobile cranes for beam & panel lifts outside to tower crane capacity Mobile cranage for establishment of contractor and client site accommodation
Mobile crane for general steel erection, facade, loading, service etc. Mobile cranage for establishment of trade contractor site accommodation
Scaffolds Scaffold and construction work method
Scaffolds Internal and external scaffold
Temporary structures Provision and maintenance of temporary roads
Temporary screens prevention items Gantries and overhead protection – Site construction
Elevated work ⦁ Construction loads, temporary propping, perimeter and void safety rails attached to formwork etc.Lift barricades
Hoisting Hoisting
Hoists, hoist driver, forklifts, loading platforms, banksman/traffic control Man and material hoists for the works including driver, base,
flag men, concrete pumping equipment, pumps, lines, booms, etc. erection, dismantling, hire, running costs, maintenance, sections, landing platforms, gates, jumping ties, communications and sundries, etc.
Elevated platforms, scissor lifts, boom lifts, knuckle booms, cherry pickers, swing stages etc. Maintenance of permanent builders’ lifts

Better procurement options and risk allocation for estimating Preliminaries costs

Responses %
Cost plus contracts or time and materials contracts 33.33
Construction management agreement/management contracting 25.93
Design and build (or novated D&C) 11.11
Lump sum (fixed price) contracts 11.11
Alliance/joint venture contracting 7.41
Procurement options are not that relevant 7.41
Term (unit price/schedule of rates) contracts 3.71

Percentage of preliminaries costs time-related (scale 0%–100%)

Sub-questions Mean (%)
Time-related (for the WHOLE duration of the project) 45.49
Combined fixed charge and time charge during the WHOLE project 19.83
Fixed (once-off payment) 18.95
Time-related but for only a shorter duration or phase of the project (not required for all the project) 15.73

Values (metrics) most useful in the pricing preliminaries categories

Question Site area m2 based Project size (GFA) area based Project size m2 height and volume considered Project value $ Other
Establishment and disestablishment of the site (getting the site up and running, and then shutting it down) 26.67 10.00 14.29 6.45 19.35
Insurances, guarantees and fees, permits, paperwork, etc. 93.33 3.23
Supervision, site staff, admin staff, Labourers, etc. 20.00 28.57 9.68 19.35
Running costs (keeping the site going – Staff excluded) 10.00 28.57 9.68 22.58
Final cleaning & handover, commissioning (Some costs at the end of the job) 60.00 28.57 3.23 12.90
Head office overheads and other costs. (e.g. finance, contingency, etc.) 53.33 22.58

Preliminary costs should be front-loaded into payment schedules

Answer %
Definitely not 13.33
Probably not 13.33
Might or might not 33.33
Probably yes 26.67
Definitely yes 13.33
Langue:
Anglais
Périodicité:
1 fois par an
Sujets de la revue:
Ingénierie, Présentations et aperçus, Ingénierie, autres