Cite

Fig. 1:

The chosen factors and their classification.
The chosen factors and their classification.

Fig. 2:

The academic qualification of responses.
The academic qualification of responses.

Fig. 3:

The practical experience.
The practical experience.

Fig. 4:

The factors and their affection percentage on constructability.
The factors and their affection percentage on constructability.

The three levels of the collected data.

Main categories Sub-category Factors Description Reference
Design attributes Standardisation and repetition Prefabrication Precast concrete, prefabricated utility products, prefabricated MEP, etc. Boton (2018), Hijazi et al. (2009), Zhang et al. (2016), and Khan (2019)
Grid layout (Horizontal/vertical/radial) grid dimensions, a repeated grid layout will lead to faster construction sequences Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Standard dimensions Dimensions for door, windows, partitions, tiles, etc. Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Economic Component flexibility Flexibility of movement of internal partitions (fixed/mobile) Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Resources availability Various resources such as building material, labour, and equipment can be approached, hired, and put to work for the execution of the project Boton (2018), Hijazi et al. (2009), Zhang et al. (2016), and Shash and Almufadhi (2021)
Labour skills Availability of special labour skills Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Team expertise The project team must be selected based on their experience knowledge and skills requirement for the project Shash and Almufadhi (2021)
Application of advance information technology Adoption of latest and modern computerised means of technology for the project Khan (2019)
Coordination or communication Coordination and communication among team members (builder and designer, site staff) Khan (2019) and Yoon et al. (2018)
Simplification of Design Designs considered efficient construction Khan (2019), Shash and Almufadhi (2021)
Construction methodology Major construction method options, in the project’s design phase Shash and Almufadhi (2021)
Structure system Structural frame types Steel frame, concrete frame, wood frame Yoon et al. (2018)
Roof types Gable, hip, Dutch, etc. Yoon et al. (2018)
Slab types Conventional, flat, waffle slabs Yoon et al. (2018)
Structural reinforcement scope The design and type of reinforcement Yoon et al. (2018)
High-strength concrete application The usage of high-strength concrete Yoon et al. (2018)
Construction attributes Space Material access Space for material storage and transportation on site Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Personnel access Accessibility of personnel for different site locations Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Equipment access Accessibility of equipment and tools for and from different site locations Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Installation Construction sequence Sequence of installation of components Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Time under ground Construction time under ground level Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Building envelope Construction of the whole building envelope Boton (2018), Hijazi et al. (2009), Zhang et al. (2016), and Yoon et al. (2018)
Weather effect Effect of climate conditions on construction work Boton (2018), Hijazi et al. (2009), Zhang et al. (2016), Khan (2019), and Yoon et al. (2018)
Safety Effect of construction sequence of workers’ safety Boton (2018), Hijazi et al. (2009), Zhang et al. (2016), and Yoon et al. (2018)
Waste management and appraisal recycling Organise and regulate the waste and convert waste into reusable products Khan (2019)
Encouragement to innovations Promotion of new ideas, the projects constructability can be enhanced using innovation ideas during the construction stage Khan (2019)
Document control Specifications The projects constructability can be enhanced by developing transparent specifications Khan (2019)
Simplification of technical specifications Detailed description of technical requirement in terms of suitability for design development of an item Khan (2019)
Qualifications, feedback and improvement in construction The projects constructability can be enhanced by utilising the lesson-learned databases and best-practices for other projects Shash and Almufadhi (2021)
Inspections and site meetings Quality of inspections and site meetings, level of knowledge sharing and capturing project objectives in accordance with client objectives Kotze and Wium (2019)
External impacts Utility availability Government facilities Availability of governmental facilities like electrical and infrastructure services Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Road-use ability Applicability of public roads for transportation Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Site impact Adjacent site Effect of current construction on adjacent constructions Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Infrastructures Effect of current construction on adjacent or nearby infrastructure constructions Boton (2018), Hijazi et al. (2009), and Zhang et al. (2016)
Other Corporate objectives Understand the project objectives as well as the client’s objectives Shash and Almufadhi (2021)
Bidding process The type of bid (design–build/ design–bid–build) Khan (2019) and Yoon et al. (2018)
Construction-driven schedule The schedules are prepared in the construction projects to keep a check on the various design and construction activities Khan (2019) and Shash and Almufadhi (2021)

Summary of the open questionnaire (expert samples).

Institutes No. of interviews Job tittle
Mayoralty of Baghdad 5 2 Senior chief engineer, senior associate engineers, chief engineer, senior engineer
Ministry of Higher Education and Scientific Research 1 Senior university lecturer
Ministry of Construction, Housing, Municipalities, and Public Works 4 Senior chief engineer, chief engineer, senior chief engineer, senior associate engineers
The new Central Bank of Iraq project 4 Project manager, consultant, chief engineer, site engineer

The values of mean, standard deviation and Cronbach’s alpha.

Categories, sub-categories and factors Mean Standard deviation Cronbach’s alpha
Design attributes 4.0556 0.71492 0.963
Construction attributes 3.6389 0.76168 0.962
External impacts 3.2778 0.88192 0.963
Standardisation and repetition 3.5556 0.84327 0.963
Economic 4 0.86189 0.963
Structure system 3.6667 0.79282 0.962
Space 3.5556 0.93944 0.962
Installation 3.6389 0.86694 0.962
Document control 3.4722 0.90982 0.963
Utility availability 3.5 0.87831 0.962
Site impact 3.7222 1.00317 0.962
Other factors 3 0.92582 0.962
Prefabrication 3.5556 0.84327 0.963
Grid layout 3.6111 0.72812 0.963
Standard dimensions 3.3611 0.83333 0.963
Component flexibility 3.4167 0.60356 0.963
Resources availability 3.9444 0.75383 0.963
Labour skills 4.0556 0.75383 0.962
Team expertise 4.1111 0.85449 0.962
Application of advance information technology 3.6111 0.80277 0.963
Coordination or communication 3.9167 0.90633 0.962
Simplification of design 3.9444 0.82616 0.962
construction methodology 3.8333 0.87831 0.963
High strength concrete application 3.3333 0.79282 0.962
Structural frames types 3.6944 0.85589 0.962
Material access 3.5833 0.76997 0.961
Personnel access 3.6389 0.99003 0.961
Equipment access 3.7222 0.88192 0.962
Construction sequence 3.6667 1.01419 0.962
Time under ground 3.5556 0.90851 0.962
Building envelope 3.25 0.87423 0.962
Weather effect 3.3611 1.07312 0.962
Safety 3.75 0.99642 0.962
Waste management and appraisal recycling 3.25 1.10518 0.962
Encouragement to innovations 3.2222 1.09834 0.962
Specifications 3.8889 0.78478 0.961
Simplification of technical specifications 3.8056 0.85589 0.961
Qualifications, feedback and improvement in construction 3.5556 0.77254 0.962
Inspections and site meetings 3.5278 0.90982 0.962
Government facilities 3.8611 0.86694 0.962
Road-use ability 3.7222 0.88192 0.962
Adjacent site 3.4444 0.73463 0.962
Infrastructures 3.5556 0.77254 0.962
Corporate objectives 3.6111 0.83761 0.962
Bidding process 3.6389 0.89929 0.962
Construction-driven schedule 3.7222 0.8489 0.962

The relative weights and developed weights.

Main categories Relative weight Sub-category Relative weight Factors Relative weight Decomposed weight
Design attributes 0.370 Standardisation and repetition 0.317 Prefabrication 0.338 0.040
Grid layout 0.343 0.040
Standard dimensions 0.319 0.037
Economic 0.356 Component flexibility 0.111 0.015
Resources availability 0.128 0.017
Labour skills 0.132 0.017
Team expertise 0.133 0.018
Application of advance Information Technology 0.117 0.015
Coordination or communication 0.127 0.017
Simplification of Design 0.128 0.017
Construction methodology 0.124 0.0 16
Structure system 0.327 Structural frames types 0.526 0.063
High-strength concrete application 0.474 0.057
Construction attributes 0.332 Space 0.333 Material access 0.327 0.036
Personnel access 0.332 0.037
Equipment access 0.340 0.038
Installation 0.341 Construction sequence 0.152 0.017
Time under ground 0.148 0.017
Building envelope 0.135 0.015
Weather effect 0.140 0.016
Safety 0.156 0.018
Waste management and appraisal recycling 0.135 0.015
Encouragement to innovations 0.134 0.015
Document control 0.326 Specifications 0.263 0.028
Simplification of technical specifications 0.258 0.028
Qualifications, feedback and improvement in construction 0.241 0.026
Inspections and site meetings 0.239 0.026
External impacts 0.299 Utility availability 0.342 Government facilities 0.509 0.052
Road-use ability 0.491 0.050
Site impact 0.364 Adjacent site 0.492 0.054
Infrastructures 0.508 0.055
Other factors 0.293 Corporate objectives 0.329 0.029
Bidding process 0.332 0.029
Construction-driven schedule 0.339 0.030
eISSN:
1847-6228
Idioma:
Inglés
Calendario de la edición:
Volume Open
Temas de la revista:
Engineering, Introductions and Overviews, other