Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
Categoría del artículo: Research Article
Publicado en línea: 29 dic 2017
Páginas: 1593 - 1603
Recibido: 01 sept 2017
Aceptado: 14 nov 2017
DOI: https://doi.org/10.1515/otmcj-2016-0022
Palabras clave
© 2017 Douglas Omoregie Aghimien et al., published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.
Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples