Trenchless technologies are employed for building sewage pipelines mainly in urban areas and when they have to be embedded deep underground. The technologies offer many advantages such as minimal earthworks and requiring limited space for their construction [7, 9, 19]. Trenchless technologies are also applied to build sewage pipelines in mining areas.
The aim of this paper is to analyse the influence of ground deformation caused by mining on sewage pipelines built using the pipe jacking method. In mining areas, such pipelines, unlike pipelines assembled in trenches, are built of butted segments, which cannot compensate for deformations of ground in pipe joints. Hence, when analysing the influence of soil deformations caused by mining on sewage pipelines built using the pipe jacking method, special attention was paid to the performance of pipe joints. In mining areas, these pipelines are subjected to additional loads and displacements, caused mainly by the influence of horizontal strains, horizontal displacements and surface curvatures. We also propose a method to consider the influence of ground deformations caused by mining on sewage pipelines built using the pipe jacking method.
Building a sewage pipeline using the pipe jacking method is employed in trenchless technologies: hydraulic jacking and microtunelling. In the microtunelling technique, pipeline sections are jacked one by one from the launch shaft into the tunnel, bored with the cutting head, forming even a few-hundred-meter-long section leading to the reception shaft (Fig. 1). The launch shaft has to accommodate all the necessary equipment. It also has to offer enough room for the jacked pipes as well as for slurry feed and return. Through the reception shaft, the boring head is taken to the surface. To secure walls of the shafts, they can be made of materials like steel sheet piles or pre-cast reinforced concrete segments using shaft sinking method. In launch shafts, the jacking frame has to be assembled. The jacking pipes for sewage pipelines are most often made of reinforced concrete, polymer concrete, or polyester resins reinforced with glass fibre or stoneware [20].
Typical microtunelling installation [15].Figure 1
In trenchless technologies employing the pipe jacking method, pipe joints should transmit longitudinal forces from one pipe to another without damaging it, keep the pipeline tight, and prevent their transverse displacement [14]. In sewage pipelines built using the pipe jacking method, the pipes are butted, without initial gaps, which is a characteristic feature of the technique (Fig. 1).
Manholes located every a few dozen meters, at most up to 100–120 meters, are an indispensable element of each sewage pipeline [14]. Manholes are built in launch shafts and reception shafts, as well as in between them, after completing the pipeline using the pipe jacking method. Manholes and pipes are connected with tight connection bells or proper connectors. The connectors are connected with stub ends, which are permanently assembled with the manhole base. To assemble manholes in large diameter pipelines, holes are made on the side or the top of a pipe. Then, we receive a very long linear object built of butted pipes (without expansion joints), usually of significant rigidity.
In static strength calculations for sewage pipelines built using the pipe jacking method, there are two stages of pipe performance: implementation and operation. At the implementation stage it is necessary to consider the transverse and longitudinal loads acting on pipeline. Longitudinal loads, acting along the pipeline axis, result from the pipe jacking force on the soil and an additional influence of, for example, steering the jacking process [2, 18, 20], The value of the maximum jacking force
where:
The ratio of stresses σm/σo is determined based on the knowledge of load eccentricity caused by the jacking force [8] if the resultant force is outside the kernel of a crosssection.
To calculate the soil load for sewage pipelines built using the pipe jacking method, Terzaghi’s theory and it’s modified versions are applied [21]. Vertical soil load
where:
Lateral earth pressure
where
Transverse influence of mining operations on a pipeline is observed from changes in ground pressure. The changes are caused by horizontal ground strains, characterised by the coefficient
Longitudinal, in relation to the pipeline, horizontal strains in the near-surface soil layer result in longitudinal forces acting on its external surface and longitudinal pipe movements. Figure 2 shows the performance of jacking pipeline joints in mining areas when pipes can freely move in tight connection bells of manholes or where expansion joints are present in the stub ends of manholes. if there are no such expansion joints, the base of a manhole may be damaged, and the displacements of pipes will be smaller.
Performance of a jacking pipeline joint in mining areas.Figure 2
During horizontal soil loosening, which constitudes the first stage of mining influence on a pipeline, the pipes extend (case 2 in Fig. 2; case 2 in Fig. 3). The extension may be uneven along the considered pipeline section due to random dispersion of the values of deformation indicators. The extreme value Δ
Pipeline section built with the pipe jacking method: 1) initial state, 2) after soil loosening, 3) after soil compaction, 4) pipeline which was subjected to the mining influence once.Figure 3
Extension in each pipe joint occurs if the value of tangent forces is greater than resistance forces in a seal in a joint. The force
where:
The value of longitudinal axial forces affecting a pipe joint equals the sum of all soil friction forces acting on the external surface of pipes or shear forces in the soil around the surface of pipes [16]. For calculations, a lower value should be assumed, which, for smooth external surface of pipes, represents friction forces. Then, the value of longitudinal axial forces
where:
The value of force
where
The value of longitudinal forces
In the second stage of mining influence on a pipeline built using the jacking method, there is horizontal compaction of a soil layer, which results in reducing gaps in the joints that were formed during the first stage (case 3 in Fig. 2; case 3 in Fig. 3). Front surfaces of the pipes return to their initial butted position, and further horizontal soil compaction causes longitudinal compression of the pipes. The maximum value of compressive force
After reaching the extreme value of strains for soil compaction, it loosens again, constituting the next, the third stage of mining influence on a pipeline. Then the pipes extend again, which results in expansions in pipe joints (case 4 in Fig. 3). It is the initial state before the influence of further mining operations. Hence, to secure a pipeline built using the pipe jacking method in mining areas, pipe joints should be longer than standard ones, similar to the length of joints of pipes embedded in trenches. Longitudinal, in relation to the pipeline, pipe joints should be able to compensate relative, extreme displacements of the pipes, resulting from horizontal strains of ground [6, 12]:
For pipelines of greater diameter, e.g.
where coefficient of variation
Due to horizontal soil loosening and compaction, caused by horizontal strains of ground, distances between manholes along the axis of a pipeline change. Horizontal soil compaction (case 3 in Fig. 3) results in shortening the distances and sliding the ends of pipes into the manholes. It may lead to damaging the base (tight connection bells and inverts), which needs to be considered while designing and assembling sewage pipelines using the pipe jacking method in mining areas. For the manholes with stub ends permanently connected with a base, the joints with pipelines should provide sufficient expansion. The displacements of the pipe ends near manholes are permanent after mining (case 4 in Fig. 3). It also should be considered while designing and building sewage pipelines using the jacking method. The total displacements of the pipe ends near the manholes ( Δ
where:
The total of displacements D
Large-diameter sewage pipelines, built with pipe jacking method, can be a long section of pipes assembled without expansion joints, as manholes of a diameter smaller than the diameter of a given pipeline are installed on the side or on the top of pipes. In such cases, it is also necessary to analyse the influence of horizontal soil displacements on the whole pipeline. Hence, a very long linear object, built of butted segments, was considered. It is capable of transmitting significant longitudinal compressive forces and relatively small tensile forces, which depend on the value of resistance force
Linear object consisting of butted segments on mining subsoil, Figure 4
The value of compressive forces acting on the pipeline within the range of main influences, i.e. along the line segment [-
where
Jacking pipes can adapt to transmit significant longitudinal forces, yet the values of longitudinal axial forces may be much higher than their bearing capacity. A pipeline built using the jacking method of GRP pipes of nominal diameter of 1.1 m, embedded at the depth of 4.0 m, will be subjected to longitudinal force of approximately 42,6 MN, once it is within the radius of main influences of 400 m (μ=0.25, γ =18.5 kN/m3). The value of the force exceeds acceptable value of the jacking force for the pipes of 3.66 MN for the wall thickness of 61 mm.
In mining areas, values of longitudinal forces, acting on the pipelines built using the jacking method without expansion joints, can be much higher than acceptable values of pipe jacking forces. Thus, it is necessary to divide such pipelines into sections and apply proper expansions in joints, calculated with equation (9). The expansions in joints lower the extreme axial forces to the values acceptable for jacking pipes.
Pipelines built using the jacking method are linear objects consisting of butted pipe segments. In mining areas, for pipelines built with the pipe jacking method, the longitudinal soil deformations are crucial. It refers mainly to the horizontal strains of ground, and for large-scale pipelines also to the horizontal displacements and subsoil curvature.
In mining areas, due to the influence of horizontal strains and longitudinal soil displacements, it is necessary to apply proper length of pipe joints and proper tight connection bells through the walls of manholes. In large-scale pipelines, expansion joints should be applied, separating segments of acceptable length, due to the bearing capacity of the pipes.
If pipelines built using the pipe jacking method are to be subjected to repetitive mining influences, their joints should have the same capabilities to compensate subsoil deformations as the pipelines embedded in trenches, as they have to interact with deformable subsoil in mining areas.